The high pressure weakened enough to allow the westerly flow to push in the marine stratus clouds. There are some breaks in a few spots allowing the sun to peak through, but some folks are going to stay socked in all day. The cloud cover will also keep the temperatures lower so the afternoon high in the mid 50s. The clouds and patchy fog will return tonight thanks to a front to the north that could squeeze out some patchy drizzle in the early morning hours when the layer is the thickest, lows near 41.

The flow turns more northerly tomorrow so we should see more of the sun, a high near 55, then more clearing overnight as the high pressure ridge builds in more so that by Sunday we are looking at a mostly sunny day, the highs up in the low 60s again.

And the sunny days continue next week sunny skies Monday and Tuesday, highs up near 63, the mostly clear nights mean, radiational cooling, so temperatures fall into the upper 30s. Some of the models suggest a low develops to the northwest which would push in some mid and high clouds later Wednesday but the high pressure ridge should work in our favor and we keep the mostly sunny skies with no precipitation through Thursday, highs still in the low 60s.

Clatsop, Tillamook, Washington and Columbia Counties state highway construction update: April 13-20

6th Through 11th Street: Waterfront Bridges (Astoria) Project (Clatsop County)

(Various Streets)

This project consists of performing work as follows:

- Install and remove temporary traffic control and pedestrian routes (TPAR)

- Install and remove temporary potable water and sanitary sewer systems

- Perform earthwork

- Install storm sewer systems and water quality structures

- Remove and reconstruct six bridges and trolley crossings (Including tracks)

- Construct roadway, sidewalks and ADA ramps

- Install permanent signs and illumination systems

- Perform additional and incidental work and called for by the Plans and Specifications

This Project replaces six aging bridges at the Astoria Waterfront, at 6th through 11th Streets and to install drainage and water quality facilities at the intersection of Highway 30 and 30th Street in Astoria. Streets will be closed while construction is occurring except for Highway 30. Flaggers will control single lane traffic while construction is occurring at 30th St. The odd numbered streets (7th, 9th and 11th) are completed, except for utility relocations underneath the structures, which is anticipated to have little to no impacts on public mobility. The even numbered streets (6th, 8th and 10th) are to be completed no later than June 30, 2020. Additionally, lane restrictions on Highway 30 and 30th street may occur during the following periods of time beginning on Monday February 24, 2020:

Lower Columbia River Highway (US-30): One Traffic Lane may be closed on the Lower Columbia River Highway (US-30) when allowed, shown, or directed during the following periods of time

Nightly, Sunday night through Friday morning, between 8:00 p.m. and 7:00 a.m.

30th Street: One Traffic Lane may be closed on 30th Street when allowed, shown, or directed during the following periods of time:

Daily, Monday through Thursday, between 9:00 a.m. and 4:00 p.m.

Friday, between 9:00 a.m. and 3:00 p.m.

Nightly, Sunday night through Friday morning, between 6:00 p.m. and 7:00 a.m.

Except for Holidays: Between noon on the day preceding a legal holiday or holiday weekend and midnight on a legal holiday or the last day of holiday weekend, except for Thanksgiving, when no lanes may be closed between noon on Wednesday and midnight on the following Sunday.

Legal holidays are as follows:

New Year's Day on January 1

Memorial Day on the last Monday in May

Independence Day on July 4

Labor Day on the first Monday in September

Thanksgiving Day on the fourth Thursday in November

Christmas Day on December 25

When a holiday falls on Sunday, the following Monday shall be recognized as a legal holiday. When a holiday falls on Saturday, the preceding Friday shall be recognized as a legal holiday.

Temporary Pedestrian Access Routes (TPAR) will be maintained throughout the work zones and will be ADA compliant.

US 101: Young’s Bay (New Youngs Bay) Bridge Repair Project (Clatsop County)

(Oregon Coast Highway, mileposts 4.53 to 5.33)

This project includes work as follows:

Install temporary traffic control and;

replacing rocker bearings;

repairing the damaged concrete with cathodic protection; and

replacing compression joint seals.

Initially in mid March, the traveling public will notice the contractor building the containment structure which will be attached to the sides of the bridge, and a barge in the water with support boats bringing crew and materials to and from the barge. Once the containment structure is in place, actual construction will begin. Most of the construction will be performed below the bridge from the barge.

The traveling public can expect periodic single lane closures at night to allow the contractor to move equipment and perform repair work on the bridge. The lane closures will be Sunday night through Friday morning, 9:00 p.m. to 5:30 a.m. A pilot car may be used to guide traffic through the lane closure. A complete two week night time closure of the bridge is scheduled in 2021 toward the end of the project.

An alternative route during periods of lane closures and the full night time closure is U.S. 101B over the Old Youngs Bay and Lewis and Clark River Bridges.

US 101: Farmer Creek Bridge Sec. (Tillamook County)

(Oregon Coast Highway, mileposts 82.74 to 83.08)

The work to be done under this Contract consists of the following:

- Construct roadbed, aggregate base and asphalt concrete pavement.

- Construct concrete curbs and islands.

- Perform earthwork

- Construct Bridge No 22654

- Install drainage, guardrail, pavement markings and signing.

- Reconstruct waterway passage.

- Perform additional and incidental work and called for by the Plans and Specifications

This Project consists of installing temporary widening to accommodate traffic, constructing most of the new bridge, realigning traffic on to the new (partial) structure, demolition of the old structure, channel reconstruction and completion of the new Bridge. There will be 24 hour flagging during the stage construction with pilot cars. Traffic restrictions employing 24 hour flagging may occur beginning:

September 1, 2019 through June 30, 2020 and September 1, 2020 through November 30, 2020 between 7:00 pm Sunday and 12:00 pm Friday. Except between 12:00 noon preceding a legal holiday or holiday weekend and midnight on a legal holiday or the last day of a holiday weekend except for Thanksgiving, when no lanes may be closed from noon on Wednesday and midnight the following Sunday. Additionally, The Clover’s Day Festival is included as a Special Event which will be regarded as a holiday for this Project.

April 10, 2020 through May 31, 2020 between 12:00 pm Friday and 7:00 pm Sunday.

Single lane traffic will be allowed nightly only:

July 1, 2020 through August 31, 2020, Sunday night through Friday morning between 5:00 pm and 11:00 am.

The Wayside will be closed for stages of construction and will be signed with the closure dates two weeks prior to being closed.

US 101: Arch Cape Tunnel Lighting Replacement Project (Clatsop County)

(Oregon Coast Highway, mileposts 35.16 to 36.42)

This project includes work as follows:

Install temporary traffic control and;

Install pedestrian and bicyclist signals on either side of the tunnel; and

Replace overhead lighting in the tunnel.

This Project consists of installing new tunnel lighting and updating the electrical system in the tunnel on US101. New signs and signals for bike access will be installed on either end of the tunnel. One or more Traffic Lanes may be closed on the Oregon Coast Highway (US 101) during the following periods of time starting January 6, 2020:

Daytime lane closures Monday – Thursday from 7:30 am to 5:30 pm

Daytime lane closures Friday from 7:30 am to 2:30 pm

After May 21, 2020 daytime lane closures will no longer be permitted. One or more Traffic Lanes may be closed at night during the following periods of time after May 21, 2020:

Nighttime lane closures Sunday night – Monday morning from 7:00 pm to 7:00 am

Nighttime lane closures Monday night – Friday morning from 6:00 pm to 7:00 am

Except for Holidays: Between noon on the day preceding a legal holiday or holiday weekend and midnight on a legal holiday or the last day of holiday weekend, except for Thanksgiving, when no lanes may be closed between noon on Wednesday and midnight on the following Sunday.

Legal holidays are as follows:

New Year's Day on January 1

Memorial Day on the last Monday in May

Independence Day on July 4

Labor Day on the first Monday in September

Thanksgiving Day on the fourth Thursday in November

Christmas Day on December 25

0
0
0
0
0

Online Poll

Who are you voting for in the State House District 32 Race in November?

You voted:

Online Poll

Who are you voting for in the State House District 32 Race in November?

You voted:

(0) comments

Welcome to the discussion.

1. Be Civil. No bullying, name calling, or insults.
2. Keep it Clean and Be Nice. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
3. Don't Threaten. Threats of harming another person will not be tolerated.
4. Be Truthful. Don't knowingly lie about anyone or anything.
5. Be Proactive. Let us know of abusive posts. Multiple reports will take a comment offline.
6. Stay On Topic. Any comment that is not related to the original post will be deleted.
7. Abuse of these rules will result in the thread being disabled, comments denied, and/or user blocked.
8. PLEASE TURN OFF YOUR CAPS LOCK.